Clay discharged at one go to the Longhuai clay storage facility
Page view:
On Feb. 26, 2017, the clay is discharged successfully at one go to the newbuilt Longhuai clay storage facility of Guangxi Huayin Alumina Industry Co., Ltd. The project is built by CINF as the EPC contractor.
Since the commencement of the project construction in 2016 and with the joint efforts of contractor, owner, supervisor and constructor, CINF has achieved the first milestone target—the 880melevation No.1 Dam in the end of 2016, and the second target two days ahead on Feb. 26, 2017. The success has solved the problem of operation of Jiangwang Clay Dam exceeding the warning clay level and ensures the mine capacity improvement.
News