The project is located in Zhuzhou, Hunan Province with capacity up to 100kt/a electrolytic lead. CINF is the first to introduce Kivcet technology to an EPCbased project. The project construction started in July, 2010 and was completed in Sept., 2012. In Mar., 2013, the project reached the design capacity.
The construction site
The central control room
The liquid lead in Kivcet furnace